Re: Material Transfer (B/w Sloc)

$
0
0

Hi Caetano,

 

 

I'll be highlighting the process so kindly let me know whether it's correct or where it needs to be corrected.

- I create production supply area through SPRO > LE > WM > Interfaces > Define Production. I assign PSA1 (production supply area 1) to Sloc 1 for 1st WorkCenter. PSA2 to Sloc 2 for 2nd WC.

- I assign respected Production supply area in cro2 to 1st and 2nd WC

~Now planning run.

-Now I do the planning(Pir, Mrp run). Then convert planned orders to Prd Orders through co41.

- now I goto MF60 select staging types : Sloc level.
-Click on Prd/Process Orders tab.

-Enter PrdOrder/process Order number in Order field and execute.

- In issue storage location column the Sloc will be showing up. ( where will the PSA shows up, is it Storage bin column? or do i click replenish proposal and system automatically replenishes the stock to PSA?).

Kindly guide me from this point forward.