Re: Production Scheduled start date system is giving 1.45 hrs extra timing

$
0
0

Hi ,

 

  I checked

----------------------------------------------------------------------------------------------------------------------------------------------

                Earliest Dates                          Latest Dates            Duratn

Queue                                                                                       0.0

Setup           24.08.2016                             24.08.2016               1.0

                    12:45:01                                 12:45:01

 

Processing      24.08.2016                           24.08.2016              20.0

                     14:08:50                                 14:08:50

 

Teardown        29.08.2016 02.09.2016     29.08.2016 02.09.2016   30.0

                  13:35:18   17:30:00              13:35:18   17:30:00

 

Wait            02.09.2016 02.09.2016       02.09.2016 02.09.2016     0.0

                  17:30:00   17:30:00              17:30:00   17:30:00

------------------------------------------------------------------------------------------------------------------------------------------------

 

I question is here i run the mrp at 11.30 of 24.08.2016 if set up time is added then system should give the timing 12.30 PM but it is Giving 12.45.

 

why the system is giving 15 min extra.

 

Regards,

LEO