Re: Capacity Levelling at activity level

$
0
0

Hi Shubham,

 

I have check points which you have highlighted:

 

  • Check in SPRO in scheduling parameter for the order type , whether you have checked the capacity check box "Generate capacity requirement"
    • In control key of network, 'Determine capacity requirement' check is enable.

 

  • Check in WC in scheduling tab , the formula has been assigned and the control key assigned to routing has checked for capacity requirements.
    • For PS WC scheduliing tab, there isn't any formula for work centre category '0006'. 

 

  • In project planning board ,  select edit -> Functions->Activate capacities
    • Already activated but still no effect getting same message.

 

  • Also , make sure that the amount of required work is  specified  (not the duration).It should be directly below the WC. The formula specified in WC creation /change will create capacity requirements and the work gets distributed as per the formula.
    • I have assigned work specified and on the basis of that work, duration is calculated automatically by selecting calculation key 'Calculate duration'.

So after doing that, still I'm not able to view result in 'CM05' report.

 

Regards,

Faizan