I think the dates in PR will even change with your next MRP run if you do not change the GR processing time, however a change in the material master will certainly create an entry in the planning file which is a prerequisite for a MRP run.
And as you just see is the release date equal to today's date, as you can't release it yesterday or on any other day in the past.